13.9 We saw in the EV example shown in Table 13.4 that there is
more actual effort spent than what the BCWP indicates on 4/5/2021
because that calculation only includes the completed tasks. Suppose
we invent another term called all actual efforts spent (AAES) to
include all the efforts spent as of the status date and then use it to
compute a new formula: EV9 = AAES / BAC.
a. Discuss your opinion of using EV9 instead of EV.
b. Because AAES is just a redefined and expanded BCWP, do
you believe the SV and CV figures will be more
representative of the true project status if we use AAES in
computing SV and CV? Why?