HKUST Canvas – Quiz: Online Quiz 3
Online Quiz 3
Started: Nov 9 at 6:55pm
Quiz Instructions
Question 1
0.15 pts
The three types of estimates on the Three point estimate are Optimistic, Pessimistic and
__________
Likely
Unlikely
Equally
Unequally
Question 2
0.15 pts
What is the most common type of dependency between activities?
finish-to-start
start-to-finish
finish-to-finish
start-to-start
Question 3
0.15 pts
The amount of time an activity can be delayed and yet not delay the project is termed
https://canvas.ust.hk/courses/44783/quizzes/86643/take
1/5
2022/11/9 19:17
HKUST Canvas – Quiz: Online Quiz 3
Total slack.
Free slack.
Critical float.
Float pad.
Slip pad.
Question 4
0.15 pts
Which of the aspects of a project could be changed after resource leveling?
The cost of a particular resource
The scope of project
The number of tasks in the Work Breakdown Structure
The amount of resources of the whole project
The start and the end dates of tasks
Question 5
0.15 pts
The highest element in the hierarchical breakdown of the WBS is ____________
The entire project
Major deliverables.
A cost account.
Sub-deliverables.
A work package.
https://canvas.ust.hk/courses/44783/quizzes/86643/take
2/5
2022/11/9 19:17
HKUST Canvas – Quiz: Online Quiz 3
Question 6
0.15 pts
Which of the following diagrams is the preferred technique for showing activity sequencing?
Network Diagram
Tree diagram
Venn Diagram
Three-dimensional diagram
Question 7
0.15 pts
The requirement for a freshly poured foundation to cure before beginning construction is an
example of which of the following dependencies between /uring concrete!nd ïnstruction¡ctivities
Finish to Start
Start to Start
Start to Finish
Finish to Finish
Any of these could be correct
Question 8
0.15 pts
The lowest element in the hierarchical breakdown of the WBS is called ____________
A deliverable.
A work package
https://canvas.ust.hk/courses/44783/quizzes/86643/take
3/5
2022/11/9 19:17
HKUST Canvas – Quiz: Online Quiz 3
A cost account.
A lowest sub-deliverable.
An object.
Question 9
0.15 pts
Which of the following is true for a critical task?
It is a task which affects the project completion date if delayed
It has some slack time
It has some free slacks
It has some float
It is part of all the critical paths
Question 10
0.15 pts
Assume there are no holidays in between, how many days does it take to complete the below
project?
6 days
8 days
10 days
https://canvas.ust.hk/courses/44783/quizzes/86643/take
4/5
2022/11/9 19:17
HKUST Canvas – Quiz: Online Quiz 3
17 days
No new data to save. Last checked at 7:16pm
https://canvas.ust.hk/courses/44783/quizzes/86643/take
Submit Quiz
5/5